Shoal Island Log Sort Access Bridge
Location: Crofton, BC, Canada
Contractor: SureSpan Structures Ltd.
This bridge was installed for the Timberwest Forest Company in 1999. The project required the demolition, fabrication and installation of a new concrete deck composite bridge. A major issue was the fact there were two underground pipes running underneath the bridge that could not be disturbed in any way. However, from start to finish, the project was completed in 14 days.